| 2005 || Decision to enter textiles (March); company founded (7 April) and incorporated as a public limited company (11 May)
| 2005 || Mohan Spintex India Limited (MSIL) was incorporated, marking the company's formal entry into the textile industry.
|-
|-
| 2006 || Commercial production begins at Unit 1, Vattigudipadu, with an installed capacity of 7,200 spindles (October)
| 2006 || Commercial production began at Unit 1, Vattigudipadu, with an initial installed capacity of '''7,200 spindles'''.
|-
|-
| 2007 || Spinning capacity doubled to 14,400 spindles; foundation laid for Phase II at Unit 1; association with Murata Machinery begins (March)
| 2007 || The company expanded its spinning capacity to '''14,400 spindles''', doubling its initial production capability.
|-
|-
| 2008 || First expansion phase complete; Unit 1 reaches 30,000 spindles (April)
| 2008 || The first phase of expansion was completed, increasing Unit 1's spinning capacity to '''30,000 spindles'''.
|-
|-
| 2009 || 40,000-spindle Unit 2 proposed (August) and approved by bankers (October); foundation laid
| 2011 || Unit 2 began commercial operations, adding '''44,064 spindles''' and substantially strengthening MSIL's yarn-manufacturing base.
|-
|-
| 2010 || Civil work begins on Unit 2 (February)
| 2012 || Unit 2 at Remalle was fully commissioned with '''4,576 open-end rotors''' and '''1,920 TFO drums''', expanding the company's capabilities in open-end yarn and twisted-yarn production.
|-
|-
| 2011 || Unit 2 begins commercial operations, adding 44,064 spindles (March)
| 2015 || MSIL entered vertical textile manufacturing with the addition of '''38,304 spindles''' and '''90 looms''', marking the beginning of large-scale weaving operations.
|-
|-
| 2012 || Unit 2, Remalle, fully commissioned with 4,576 open-end rotors and 1,920 TFO drums, adding open-end and twisted yarn; 36 gins
| 2016 || Further capacity was added with '''9,120 spindles''' and '''66 looms''', supporting higher yarn output and expanded fabric production.
|-
|-
| 2013 || Two-phase project proposed, including the first looms; foundation laid for Unit 3
| 2016–17 || Preparatory work was undertaken for Unit 4, laying the groundwork for the company's next phase of expansion.
|-
|-
| 2015 || Entry into vertical manufacturing: 38,304 spindles and 90 looms added at Unit 3, beginning large-scale weaving (April)
| 2020 || The company completed a major forward-integration phase by adding '''168 looms''', a processing facility with a capacity of '''1,00,000 metres per day''', and a Cut, Make and Trim (CMT) unit capable of producing '''10,000 sheet sets per day'''.
|-
|-
| 2016 || Further capacity added: 9,120 spindles and 66 looms (October)
| 2022 || A '''10.8 MW solar power project''' was commissioned, strengthening MSIL's commitment to sustainable and cost-efficient manufacturing.
|-
|-
| 2016–17 || Preparatory work undertaken for Unit 4, Mallavalli
| 2025 || MSIL expanded beyond industrial operations into education with the establishment of Mohan's Sri Vijnana Vihara School.
|-
|-
| 2017 || About 2,800 employees; cover story in ''The Textile Magazine''
| 2026 || MSIL added '''39,936 spindles''', further strengthening its spinning capacity and supporting continued growth in yarn manufacturing.
|-
| 2018 || Unit 4, Mallavalli, foundation laid
|-
| 2019 || Unit 4, Mallavalli, inaugurated
|-
| 2020 || Forward integration completed: 168 looms added, a processing plant of 1,00,000 metres a day and a cut, make and trim unit of 10,000 sheet sets a day (March); Astara brand launched
|-
| 2022 || 10.8 MW solar power project commissioned at Unit 2
|-
| 2025 || Mohan's Sri Vijnana Vihara School opens; founder elected Chairman of KRIBHCO
|-
| 2026 || 39,936 spindles added; foundation laid for new corporate office; LEAD leadership programme; Union Textiles Minister visits Mallavalli
|}
|}